Pamban bridge: India's first vertical lift bridge over sea in Rameswaram faces 'curve' test.


Date: 10-04-2024
Subject: Pamban bridge: India's first vertical lift bridge over sea in Rameswaram faces 'curve' test
New Delhi: A sharp curve in the upcoming Pamban railway bridge, India's first vertical-lift bridge connecting the country's mainland with Rameswaram island, has become an additional challenge for the Railways besides its mechanical peculiarity and a rough sea. The Rail Vikas Nigam Limited (RVNL), which is constructing this 2.08-km-long bridge, is facing a huge challenge in moving a lift span, which is 72.5-m-long, 16-m-wide and weighs 550 tonne, from the Rameshwaram end to 450 m in the sea to fi ..

"We started moving this lift span on March 10 and till date, we have moved the 550 ton lift span 80 m towards the centre of the bridge. The biggest challenge is the 2.65 degree of curved alignment of the bridge. Had it been straight, we would have moved it faster," a senior official of RVNL said, adding the curved shape was essential due to various alignment changes.


The movement of lift span to its final fixing point shall be completed by the end of May, as it still has to be carried 370 m more.

"Once we cross the curved portion, we can expedite its movement. We have taken a huge precaution while moving it in the sea as its size and weight requires great precision at each step," the official said.

The RVNL got this lift span designed from Spanish firm TYPSA and it was manufactured at Sattirakkudi Railway Station, which is 20 km away from the sea coast.


"We brought it in various parts and assembled it here at the coast because it was not possible to carry such a huge structure from the manufacturing point," the RVNL official said.


The train services between Mandapam in the mainland and Rameswaram island were suspended on December 23, 2022 after the existing rail bridge, which was built in 1913, was declared non-operational from the safety point of view.


"When the Pamban bridge was operational, trains used to move to the bridge and reach Rameshwaram. They used to move slowly on the Pamban bridge and reach the pilgrimage town in about 15 minutes," a Southern Railway official said.


At present, all trains terminate at Mandapam and people use road routes to reach Rameswaram. Prime Minister Narendra Modi laid the foundation stone of the new bridge, parallel to the old one, in November 2019 and the work was started in February 2020 by RVNL.


It was supposed to be completed by December 2021, however, the deadline was extended due to the COVID-19 pandemic.


According to the Southern Railway, the 2.08-km-long bridge will allow the Indian Railways to operate trains at a higher speed and it will also increase traffic between the mainland of India and Rameswaram island.


Till a road bridge was constructed in 1988, train services were the only link connecting Mandapam to Rameswaram island situated in the Gulf of Mannar.


According to the Southern Railway, the substructure of the bridge has been built for the double lines and the navigational span will also have provision for double lines.

 Source Name : Economic Times

Get Sample Now

Which service(s) are you interested in?
 Export Data
 Import Data
 Both
 Buyers
 Suppliers
 Both
OR
 Exim Help
+


What is New?

Date: 12-04-2024
NOTIFICATION No. 09/2024 – CENTRAL TAX
Seeks to extend the due date for filing of FORM GSTR-1, for the month of March 2024

Date: 10-04-2024
NOTIFICATION No. 08/2024- Central Tax
Seeks to extend the timeline for implementation of Notification No. 04/2024-CT dated 05.01.2024 from 1st April, 2024 to 15th May, 2024

Date: 08-04-2024
Notification No 07/2024 – Central Tax
Seeks to provide waiver of interest for specified registered persons for specified tax periods

Date: 04-04-2024
Notification No. 27/2024 - Customs (N.T.)
Exchange Rate Notification No. 27/2024-Cus (NT) dated 04.04.2024-reg

Date: 26-03-2024
Notification No. 24/2024 - Customs (N.T.)
Exchange Rate Notification No. 24/2024-Cus (NT) dated 26.03.2024-reg

Date: 14-03-2024
NOTIFICATION No. 17/2024-Customs
Seeks to amend notification No. 57/2017-Customs dated 30.06.2017 so as to modify BCD rates on certain smart wearable devices.

Date: 12-03-2024
NOTIFICATION No. 15/2024-Customs
Seeks to amend specific tariff items in Chapter 90 of the 1st schedule of Customs Tariff Act, 1975.

Date: 12-03-2024
NOTIFICATION No. 16/2024-Customs
Seeks to amend Notification No. 50/2017-Customs dated 30.06.2017 so as to change the applicable BCD rate on specified parts of medical X-ray machines.

Date: 07-03-2024
Notification No. 18/2024 - Customs (N.T.)
Exchange Rate Notification No. 18/2024-Cus (NT) dated 07.03.2024-reg

Date: 06-03-2024
Notification No. 13/2024-Customs
Seeks to amend notification No. 50/2017- Customs dated 30.06.2017, in order to reduce the BCD on imports of meat and edible offal, of ducks, frozen, subject to the prescribed conditions, with effect from 07.03.2024.



Exim Guru Copyright © 1999-2024 Exim Guru. All Rights Reserved.
The information presented on the site is believed to be accurate. However, InfodriveIndia takes no legal responsibilities for the validity of the information.
Please read our Terms of Use and Privacy Policy before you use this Export Import Data Directory.

EximGuru.com

C/o InfodriveIndia Pvt Ltd
F-19, Pocket F, Okhla Phase-I
Okhla Industrial Area
New Delhi - 110020, India
Phone : 011 - 40703001