Subject: |
Regarding settlement of disputes between one Govt. Department and another and one Govt. Department and a Public Enterprise and one Public Enterprise and another
|
Regarding settlement of disputes between one Govt. Department and another
and one Govt. Department and a Public Enterprise and one Public Enterprise and
another
Circular
No. 329
dated 14th August 1997
I
am directed to invite your attention to Board's Circular No. 27/27/94-CX dated
2.3.94 issued from F.No. 390/140/93-JC wherein it was directed that whenever any
appeal/ petition is prepared to file by the Department before any Court or
Tribunal in a matter relating to PSU, the Commissioner should send a self
contained proposal for consideration of the Committee on Disputes along with
relevant enclosures to the Board. As per the Supreme Court order dated 7.1.94
enclosed with the above instructions even in respect of pending cases clearance
was to be obtained from the Committee on Disputes.
2.
Instances have come to the notice of the Board where/ in the above
regard, proposals have not been received in time from the Commissioners and it
is only after the CEGAT asked for the clearance of COD that the proposals are
being sent by the Commissioners for immediate/ urgent clearance of the COD.
3.
The Board desires that the Commissioner should personally review all the
cases where clearance of COD is required but which might have yet not been
referred to for required clearance of the COD. In respect of all such cases,
proposals should be sent immediately to the Board enclosing the relevant
documents particularly S.C.N., order-in-original, Appeal order, Memorandum of
appeal, etc.
4.
In future it should be ensured that all such cases are promptly referred
to for COD clearance.
|
|