Highway building gathers pace in Q1.


Date: 04-07-2023
Subject: Highway building gathers pace in Q1
Highway construction accelerated 9.4% year-on-year in the first quarter of this financial year, but new contracts fell to a five-year low, showed data available at June-end.

During the quarter, 2,150 kilometres of highways were built, but new projects for only 600 km were awarded, said officials.

India had constructed 1,966 km and awarded 969 km of highways in the corresponding months a year ago.


“Highway construction for the first quarter of the fiscal is higher than the average of the last four years, which stood at 2,057 km,” a senior official told ET on condition of anonymity.

Highways would have been constructed at a faster pace but for the irregular rains, said officials. Sector watchers said the upcoming state assembly elections in December could also cause some delays once the model code of conduct for the polls kicks in.

According to highway contractors, delayed payments also impacted activity.


Highway builders also claim they are not getting due bonuses for timely completion of projects and that there is a shortage of field officers to grant speedy approvals for work that has been done.

“There is lower discretion in the construction framework, and the priority is only cost.


So, of late, contractors have not been satisfied with the payment redress mechanism, which is bent in favour of the government,” an industry executive told ET, adding that absence of senior bureaucrats in key positions of the National Highways Authority of India (NHAI) is also a concern.

Source Name: Economic Times
 

Get Sample Now

Which service(s) are you interested in?
 Export Data
 Import Data
 Both
 Buyers
 Suppliers
 Both
OR
 Exim Help
+


What is New?

Date: 02-05-2024
Notification No. 34/2024 - Customs (N.T.)
Exchange Rate Notification No. 34/2024-Cus (NT) dated 02.05.2024-reg.

Date: 18-04-2024
Notification No. 30/2024 - Customs (N.T.)
Exchange Rate Notification No. 30/2024-Cus (NT) dated 18.04.2024-reg.

Date: 12-04-2024
NOTIFICATION No. 09/2024 – CENTRAL TAX
Seeks to extend the due date for filing of FORM GSTR-1, for the month of March 2024

Date: 10-04-2024
NOTIFICATION No. 08/2024- Central Tax
Seeks to extend the timeline for implementation of Notification No. 04/2024-CT dated 05.01.2024 from 1st April, 2024 to 15th May, 2024

Date: 08-04-2024
Notification No 07/2024 – Central Tax
Seeks to provide waiver of interest for specified registered persons for specified tax periods

Date: 05-04-2024
Notification No. 23/2024-Customs
Seeks to amend No. 64/2023-Customs, dated the 7th december, 2023 in order to allow duty free imports of yellow peas with bill of lading issued on or before 30.06.2024

Date: 04-04-2024
Notification No. 27/2024 - Customs (N.T.)
Exchange Rate Notification No. 27/2024-Cus (NT) dated 04.04.2024-reg

Date: 02-04-2024
Notification No. 22/2024-Customs
Seeks to fully exempt the applicable export duty on exports of Kalanamak rice not exceeding 1000 MTs subject to the specified conditions.

Date: 26-03-2024
Notification No. 24/2024 - Customs (N.T.)
Exchange Rate Notification No. 24/2024-Cus (NT) dated 26.03.2024-reg

Date: 14-03-2024
NOTIFICATION No. 17/2024-Customs
Seeks to amend notification No. 57/2017-Customs dated 30.06.2017 so as to modify BCD rates on certain smart wearable devices.



Exim Guru Copyright © 1999-2024 Exim Guru. All Rights Reserved.
The information presented on the site is believed to be accurate. However, InfodriveIndia takes no legal responsibilities for the validity of the information.
Please read our Terms of Use and Privacy Policy before you use this Export Import Data Directory.

EximGuru.com

C/o InfodriveIndia Pvt Ltd
F-19, Pocket F, Okhla Phase-I
Okhla Industrial Area
New Delhi - 110020, India
Phone : 011 - 40703001